Storm water / Rain Water Harvesting: • Study existing contour plan and determine economical alignment for storm water drainage system. • Collect data with respect to total rainfall, rainfall intensity, contributing area etc. • To prepare drawing of identified alignments for execution purpose. • To prepare drawings for appurtenances like inlet drain, chambers/ man holes etc. • Design / prepare storm water harvesting system for roof top as well as area drainage. • Prepare bill of quantities. |
Drainage/ Sanitation: • Study existing contour plan and decide tentative pipeline alignment for sewage. • Study alignment survey details at site and prepare relevant drawings for laying sewer. • Prepare detailed specifications for piping system. • Prepare drawings for other work like manhole, flushing tank and bathroom/toilet/drawings etc. • Prepare bill of quantities. • Work out cost estimates for drainage system. |
![]() |